Measurement, control and interpretation
Geotechnical monitoring measures over time how the ground and the works that interact with it behave. NHAZCA combines field instrumentation, radar interferometry and image-based analysis, and delivers interpreted measurement series: it is a measurement and reading service, not just an instrument supply.
Field instrumentation
Inclinometer and piezometer monitoring
InSAR and ground-based radar
PhotoMonitoring™
Analysis and reporting
The definition
Geotechnical monitoring is the planned and repeated observation of the behaviour of the ground, of geotechnical works and of structures that interact with the ground, in order to recognise changes against a stated reference condition.
It is a continuous process, not a single investigation: a series of comparable measurements makes it possible to tell a real trend from an isolated reading, within the geological and geotechnical model of the site.
01
The phenomenon, the quantities to be observed, the measurement geometry, the frequency and the limits are defined before the instruments are chosen. Without a site model, a measurement has no context in which to mean anything.
02
A stated baseline, campaigns repeated with the same geometry and documented quality checks: these are the three conditions under which two readings taken months apart can be compared at all.
03
Maps, time series and interpretive notes connect the measurement to the decision without hiding its limits. The measurement describes what has happened; the decision remains with whoever operates the asset or the site.
ISO 18674-1:2015 sets out general rules for performance monitoring by field instrumentation of ground, of structures interacting with the ground and of geotechnical works. Geotechnical monitoring measures and documents: it does not replace design verification, ground investigation or the safety assessments that remain the responsibility of the designer or of the asset operator.
The quantities
The quantities measured in geotechnical monitoring are the movements of the ground and of the works that interact with it, the pressure of water in the ground, and the environmental conditions that affect how those movements are read. Each quantity has its own unit and a technique that observes it better than the others.
In specifications and reports the same activity appears under different names: displacement monitoring, ground deformation monitoring, settlement monitoring. These are not three different services; they are the same measurement plan named after the quantity that matters most in that particular project. What changes is the instrument and the frequency, not the method.
Quantity measured
Unit
Technique that observes it
Quantity measured
Surface displacement
Unit
mm; mm/year as a rate
Technique that observes it
Satellite InSAR, ground-based radar interferometry, survey benchmarks
Quantity measured
Displacement at depth
Unit
mm
Technique that observes it
In-place and probe inclinometers in boreholes
Quantity measured
Settlement
Unit
mm
Technique that observes it
Precise levelling, settlement plates, satellite InSAR
Quantity measured
Pore water pressure, groundwater
Unit
kPa; m of water column
Technique that observes it
Piezometers
Quantity measured
Strain
Unit
µε (microstrain)
Technique that observes it
Extensometers and strain gauges
Quantity measured
Rainfall and temperature
Unit
mm; °C
Technique that observes it
Environmental sensors installed with the instrumentation
From orbit
Wide area
Satellite InSAR observes ground movement over wide areas and reconstructs historical series where stable radar targets exist. It requires no installation on site.
From the ground, at a distance
One face at a time
Ground-based radar interferometry and image-based analysis observe a slope, an excavation face or a wall from a fixed position, at a frequency decided in the monitoring design.
At the surface
The instrumented point
Survey benchmarks, extensometers, crack gauges and load cells measure where they are installed: coverage depends on how many points are instrumented and where.
Below ground
Under the ground surface
Inclinometers and piezometers measure inside the borehole, along the instrumented vertical. This is the only row that reaches below the surface, and no remote technique replaces it.
The four rows are not alternatives: they answer different questions and are combined only when the combination adds information.
A list of quantities is not a monitoring design: for each of them the measurement geometry, the acquisition frequency and the limits must be stated, otherwise the series is not comparable over time.
Instruments in the ground
Geotechnical instrumentation is the set of sensors installed in the ground, in boreholes or on structures to measure how they behave. Instrumentation on its own produces readings; monitoring is what turns those readings into a series that can be compared over time and read against a site model.
Inclinometer monitoring answers one question that no remote technique can answer: at what depth the ground is moving. The probe is lowered into a guide casing at regular depth intervals and the reading is repeated with the probe rotated by 180 degrees, so that the systematic error of the instrument cancels in the average of the two runs; comparison with the reference reading returns the displacement profile along the instrumented vertical. A single campaign does not demonstrate movement: it describes a state.
Piezometer monitoring measures the pressure of water in the pores of the ground at the level where the instrument sits, and from it the groundwater level at that point. The value changes with rainfall, with works going on nearby and with the season, so it only becomes meaningful inside a series and alongside the rainfall record. A piezometer describes the instrumented point, not the whole aquifer.
The two measurements do not replace one another and are often read together: a change in displacement at depth that coincides with a rise in pore water pressure says something that neither measurement would say on its own. Both require a stated reference reading and campaigns repeated with the same procedure, otherwise they describe a value and not a trend.
Aspect
Inclinometer
Piezometer
Aspect
What it measures
Inclinometer
The tilt of the guide casing against the vertical
Piezometer
The pressure of water in the pores of the ground
Aspect
What is derived from it
Inclinometer
The displacement profile along the instrumented vertical
Piezometer
The groundwater level at the instrument depth
Aspect
Where it measures
Inclinometer
Along the whole casing, at regular depth intervals
Piezometer
At one point only, at the installation depth
Aspect
What conditions the reading
Inclinometer
Stability of the reference reading and repeatability of the procedure
Piezometer
Rainfall, adjacent works and seasonality
Aspect
When it is chosen
Inclinometer
When you need to know at what depth the ground is moving
Piezometer
When the behaviour of the ground depends on water
If you are looking for where to buy an inclinometer or a piezometer, this is not the right page: NHAZCA does not sell geotechnical instruments. If instead you have to decide what to measure, at what depth, how often, and how to read the data together with the other observations from the site, this page describes exactly that service.
Downward movement
Settlement monitoring follows the downward movement of a specific work — a fill, a foundation, the ground next to an excavation — against a reference reading; subsidence monitoring instead follows the lowering of the ground surface over an area much larger than any single work, and over a much longer time.
Settlement develops while a fill is being placed, while a foundation takes load, and while the ground beside an excavation redistributes stress. It is measured in millimetres against a reading taken before the works began, with precise levelling, settlement plates and, where stable radar targets exist, satellite InSAR. Pore water pressure is normally read alongside it, because in fine-grained soils it is the water leaving the pores that governs how the settlement evolves.
Subsidence is a regional lowering of the ground surface, driven by processes that act over years — groundwater withdrawal, compaction of soft deposits, underground extraction. Because it affects an area rather than a point, it is normally screened from orbit: satellite InSAR reconstructs velocity fields and historical series over a whole territory, and identifies where a denser, instrumented programme is worth designing. What the satellite cannot tell you is at what depth the movement originates.
Aspect
Settlement
Subsidence
Aspect
What is moving
Settlement
A specific work, or the ground immediately around it
Subsidence
The ground surface over an area, regardless of what stands on it
Aspect
Typical extent
Settlement
Metres to hundreds of metres
Subsidence
Kilometres
Aspect
How it is usually observed
Settlement
Precise levelling, settlement plates, in-situ instrumentation
Subsidence
Satellite InSAR screening, with in-situ instrumentation where it is needed
Aspect
What conditions the reading
Settlement
Stability of the benchmark and continuity through the construction phases
Subsidence
Availability of stable radar targets and line-of-sight geometry
Neither settlement nor subsidence is a defect in itself: both are expected behaviours of the ground, and monitoring exists to show whether what is happening matches what was expected. Acceptance criteria, thresholds and any response procedure are defined by the designer, the supervising engineer or the asset operator on the specific case, not by the measurement.
The NHAZCA approach
A geotechnical monitoring programme does not start from an instrument catalogue: it starts from the geological and geotechnical model of the site and from the decisions it has to support, and only then chooses the configuration. An instrument is useful only if it measures the required quantity with an adequate geometry, depth, sensitivity and frequency.
Interpretation runs alongside acquisition: it does not arrive at the end as an attachment. And once started, the configuration has to hold for the whole planned duration: moving a benchmark, changing the probe or increasing the reading frequency halfway through breaks the comparability of the series and must be stated in the report.
1
The phenomenon to observe, the decisions to support, responsibilities and limits.
2
Instruments, measurement points, depths, geometries, frequencies and baselines.
3
On-site and remote measurements, with repeatable procedures.
4
Quality checks, continuity of the data and operating conditions.
5
Maps, time series and technical notes with the limits stated.
Complementary techniques
Below ground, at the surface and from a distance, different quantities are observed. Field instrumentation and remote sensing are not interchangeable: each keeps its own measurement geometry, resolution, frequency and sensitivity to site conditions. Combining them is worth doing when the combination adds information, not for the sake of a complete catalogue.
Inclinometers, piezometers, extensometers, crack gauges, load cells and survey benchmarks measure where they are installed, at high frequency and with clear limits. They are the only way to observe what happens below the ground surface, but they describe the instrumented point: coverage depends on how many points are instrumented and where.
Radar from a fixed position produces maps and time series of the displacement component along the line of sight, observing one face at a time. Signal coherence, vegetation and viewing geometry condition how readable the result is.
Processing satellite radar archives makes it possible to observe ground movement over wide areas and to reconstruct historical series covering past periods, with nothing installed on site. Stable radar targets are required, and the observed component remains the one along the satellite line of sight.
Multi-temporal imagery supports digital image correlation and change detection on slopes, excavation faces and earth works. Vegetation, lighting, site activity and image co-registration must be told apart from actual deformation. Results are delivered through the IRIS platform.
When the behaviour of a structure above ground depends on the founding soil or on works going on nearby, geotechnical monitoring should be designed together with structural health monitoring: the ground and the ground–structure interaction belong to this page, the structure above ground to its own.
Choosing the technique
The configuration follows the engineering requirement and the site model, not the instrument that happens to be available.
Requirement
Possible technique
Output
Limit to consider
Requirement
Knowing at what depth the ground is moving
Possible technique
Inclinometers in boreholes
Output
Displacement profiles along the vertical, against the reference reading
Limit to consider
Requires a baseline and campaigns repeated with the same procedure
Requirement
Understanding whether the behaviour depends on water
Possible technique
Piezometers, read together with the rainfall record
Output
Pore water pressure series and groundwater levels
Limit to consider
A single campaign does not describe a trend
Requirement
Following the displacement field of a face or a slope
Possible technique
Ground-based radar interferometry
Output
Displacement maps and time series
Limit to consider
Line-of-sight component, signal coherence and instrument position
Requirement
Observing ground movement over a wide area
Possible technique
Satellite InSAR
Output
Velocities and historical series on radar targets
Limit to consider
Coverage, geometry and coherence are not uniform; stable targets are required
Requirement
Telling visible changes apart from deformation
Possible technique
PhotoMonitoring™, digital image correlation and change detection
Output
Thematic maps and control points
Limit to consider
Separating deformation from lighting, vegetation and site activity
Requirement
Reading the interaction between ground and structure above
Possible technique
Field instrumentation coordinated with structural health monitoring
Output
Comparison between ground quantities and structural quantities
Limit to consider
Requires two coordinated plans and one common time base
The deliverables
Continuous monitoring produces a lot of data, but the value is not in the quantity: it is in a technical picture that makes trend, quality and limits of the observations visible.
Objectives, configuration, reference readings, frequencies, roles and exclusions, agreed before installation.
How the quantities evolve at the points and over the periods observed, with the measurement geometry stated.
Coverage, continuity, interruptions and the environmental conditions that affect the data.
Comparisons, items requiring attention and limits of validity, without over-reading the measurement.
Applications
The method is the same; what changes is the object observed, the installation constraints and the kind of decision that has to be supported.
During an excavation the equilibrium of the ground changes by construction. Excavation monitoring needs a reference reading taken before the works start and continuity of measurement through the critical phases — on the face, on the retaining works and on the buildings around them.
Convergence, face extrusion and interaction with the surrounding ground are observed with measurements designed around the advance rate and the support type, at a frequency that follows the site and not the calendar.
Settlement monitoring follows how fills, embankments and foundation levels settle during construction and in service, together with the pore water pressures that govern how that settlement evolves.
When the behaviour of a structure depends on the founding soil or on works going on nearby, the geotechnical reading is coordinated with structural health monitoring: two distinct plans, one common time base.
In-situ and remote measurements integrated with the model of the phenomenon and with the management objectives. Where the phenomenon is an active landslide, the dedicated service is the landslide monitoring system.
At territorial scale, satellite observations serve to set priorities and to decide where a denser, instrumented programme is worth designing. The asset-management layer above it is described in SGAM.
From method to practice
A geotechnical monitoring programme only really exists once the instruments are installed, the reference readings have been taken and the chain that runs from sensor to report has been verified at least once. NHAZCA integrates on-site and remote techniques while keeping measurement geometry, data quality and the field of validity visible.
Every result stays tied to the site, to the period observed and to the configuration adopted: published case studies show the method, they do not replace the specific design of a new measurement programme.
Further reading
Standards and public technical sources useful for understanding the scope and the limits of the methods described above.
ISO 18674-1:2015 — Geotechnical monitoring by field instrumentation. Part 1: General rules
General framework for performance monitoring by field instrumentation of ground, of structures interacting with the ground and of geotechnical works.
ISO 18674-3:2017 — Measurement of displacements across a line: Inclinometers
Reference for the measurement of displacements along a line using inclinometers.
NCHRP Synthesis 89 — Geotechnical Instrumentation for Monitoring Field Performance, J. Dunnicliff
Public synthesis on instrument selection, installation and the reading of field measurements in geotechnical construction.
Copernicus — European Ground Motion Service
European ground-motion products derived from Sentinel-1 InSAR processing.
EGMS product description
Technical description of the Basic, Calibrated and Ortho products and of their measurement geometry.
Cosentino, Brunetti and Mazzanti (2025) — Photomonitoring as a tool for monitoring landslides
Scientific paper on optical sensors and digital processing techniques applied to the study of deformation processes.
FAQ
What is geotechnical monitoring?
Geotechnical monitoring is the planned and repeated observation of the behaviour of the ground, of geotechnical works and of structures that interact with the ground, in order to recognise changes against a stated reference condition. It measures displacement at the surface and at depth, settlement, pore water pressure and strain, together with the environmental conditions that affect those readings. It is a continuous process, not a single investigation: only a series of comparable measurements can tell a real trend from an isolated reading.
What does geotechnical mean?
Geotechnical refers to the behaviour of soil and rock and to the way engineering works interact with them. A geotechnical problem is therefore one where the ground is part of the answer: the stability of a slope, the settlement of a foundation, the pressure of water in the pores of a soil. It is the reason this page is about the ground and the ground–structure interaction, while the behaviour of the structure above ground belongs to structural health monitoring.
What is geo monitoring?
Geo monitoring is the short form commonly used for geotechnical monitoring, that is the repeated measurement of how the ground and the works interacting with it behave over time. The short form appears mostly in procurement documents and in supplier catalogues; the activity it names is the same one described on this page.
What instruments are used in geotechnical monitoring?
The instruments most often used are inclinometers, which measure the tilt of a borehole casing and return displacement at depth; piezometers, which measure pore water pressure and therefore the groundwater level at one point; extensometers and settlement plates, which measure vertical displacement and settlement; tiltmeters, which measure the rotation of a structural element; strain gauges and load cells, which measure strain and load in anchors and props; and crack gauges, which measure the opening of a crack over time. Remote techniques such as satellite InSAR and ground-based radar interferometry add surface coverage that point instruments cannot give, but none of them measures below the ground surface.
What is the difference between an inclinometer and a piezometer?
An inclinometer measures a movement, a piezometer measures a pressure. The first returns the displacement along the instrumented vertical against a reference reading; the second returns the pressure of water in the pores of the ground, and therefore the groundwater level, at the single point where it is installed. They are different and complementary pieces of information: on many sites they are installed in the same borehole or in nearby boreholes precisely so that they can be read together.
What is the difference between settlement and subsidence?
Settlement is the downward movement of a specific work or of the ground immediately around it, over metres to hundreds of metres, and it is normally driven by construction: a fill being placed, a foundation taking load, an excavation redistributing stress. Subsidence is the lowering of the ground surface over an area of kilometres, driven by processes that act over years such as groundwater withdrawal or the compaction of soft deposits. Settlement monitoring is usually built on levelling and in-situ instrumentation; subsidence monitoring usually starts from satellite screening and adds instruments where the screening shows they are needed.
How much does a geotechnical report cost?
A geotechnical report and a geotechnical monitoring programme are two different things, and it is worth separating them before talking about cost. A geotechnical report normally documents a ground investigation — boreholes, sampling, laboratory tests — carried out once to characterise the site. Monitoring is a service that runs over time: it measures how that site behaves during and after the works. NHAZCA delivers the second, and the cost of a monitoring programme does not follow the price list of the first.
How much does geotechnical monitoring cost?
Cost follows the scope: objectives, site and access conditions, the mix of techniques, the number and depth of instrumented points, acquisition and reporting frequency, duration, and the deliverables required. Without these elements a figure would not be technically meaningful. It is also worth distinguishing the cost of the instrument from the cost of the monitoring: an instrument bought and read badly costs more than one hired and read well. Share your brief for a scoped estimate.
How do you monitor slope movement?
Slope movement is monitored by combining what happens at the surface with what happens below it: inclinometers give the displacement profile with depth and identify the sliding surface; piezometers show whether water is driving the movement; ground-based radar interferometry and image-based analysis follow the displacement field of the whole face; satellite InSAR provides the wide-area and historical context. Which of these enter the plan depends on the mechanism suspected and on the decision to be supported. Where the phenomenon is an active landslide, the dedicated service is the landslide monitoring system.
What does "geotechnical services" mean?
Geotechnical services is an umbrella term that different suppliers fill differently: it can mean ground investigation, laboratory testing, geotechnical design, instrumentation supply, or monitoring. Because the term is broad, a proposal is only comparable if it states which of these are actually included. What NHAZCA provides under geotechnical monitoring services is the measurement side: designing the observation, acquiring or coordinating the readings, validating them and interpreting them over time.
Can remote sensing replace in-situ instrumentation?
Not as a general rule. Satellite and ground-based radar, imagery and point instruments observe different components at different spatial scales, and none of the remote techniques measures below the ground surface. They may complement one another, and remote screening often decides where in-situ instruments are worth installing, but substituting one for the other has to be justified against the monitoring objective and stated explicitly.
How are acquisition and reporting frequency selected?
They are agreed from the expected behaviour, the project phase, the timescale of the decision, access conditions, instrument capability, data quality and reporting needs. Acquisition frequency and reporting frequency may well be different: a sensor can read every hour while the technical report is issued monthly. Whatever is chosen has to hold for the planned duration, because changing the frequency halfway through breaks the comparability of the series.
Does geotechnical monitoring replace design checks and safety assessments?
No. Monitoring provides measurements and technical interpretation; ground investigation, design verification and safety assessment remain the responsibility of the designer, of the supervising engineer or of the asset operator. Monitoring does not on its own prevent a failure and does not predict one: it makes a change visible, describes its magnitude and trend, and leaves the assessment to whoever has the competence for it. Any thresholds and escalation procedures must be defined explicitly by those parties for the specific scenario.
Why NHAZCA
We do not resell third-party instrument catalogues: we design the measurement, acquire or coordinate it, validate it and interpret it over time. For our own NHAZCAM stations, the main offer is a monitoring system configured for the site, with NHAZCA services.
Satellite and ground-based InSAR and PhotoMonitoring™ observe the ground where installing instruments is difficult, unsafe or inappropriate.
The method comes out of a university research background and stays anchored to the technical literature on geotechnical monitoring.
Measurement geometry, depth, data quality, environmental conditions and temporal validity stay visible in every deliverable.
Preliminary assessment
Share the objectives, the context and the constraints: the first step is deciding which quantities to observe, at what depth, with which techniques and within which limits.